Hi,
I'm back using P6 after a few years off and have been tasked with creating a resource histogram that shows the remaining hours.
Each time I run the report it is showing me the remaining actual units and not the remaining to earn.
eg.
Budget = 240, % Comp = 95%, Actuals = 210, Earned = 228
When I run the report it should tell me I have 12 hrs left remaining, however it says I have 30 hrs left.
I have my activities set up as Task Dependant, Fixed Duration & Units & Physical % Complete.
Any ideas?
Many thanks,
Gavin