Dear all
I am facing a problem with a 5000 activity Program. The Contractor gave the relations with FF, SS & FS.I observed that some of the activities don't have Finish to start relations only FF relations. Please help me filter all the activities which don't have Finish to start relations.
Regards
Arun.V