I am currently in the role of project controls. I receive from our contractors a weekly update in the form of a file to upload into P6. Once I have imported or uploaded the project plan I will ensure the milestones are connected and then produce a complete start to finish integrated plan. Included is a commissioning schedule.
My question may be simple but is there a way or does the P6 program merge the next week plan replacing only the updated items or does it replace completely deleting the interconnecting links I made to each plan. All schedulers work on standalone machines and they submit a new file each week.
Any help is appreciated.