I saw a scheduler do this once in P6 and I trying to replicate what he did.
Say I need to be Finished on 12/31/19 and I have a schedule built out. How can I schedule from that date backwards essentially given me the latest start of all activities to achieve that Must Finish by date?
In other words, I am trying to figure out how to schedule all activities from a finish MS backwards. Nothing hitting the Data Date until it gets to the start of the first activity in that chain of logic.
Jeff