- Develop Project Activities
- Design Project Activities Logics
- Estimate project activity resources
- Estimate project Activity duration
- Establish Project major and minor milestone
- Analyze/Review project schedule output
- Review and Integrate Sub-contractors Schedule into Overall Project Schedule
- Baseline Project Schedule
- Develop Project Bidding Schedules
- Develop Project Measurement Template and Project Plan S-Curve
- Document/Report Daily, Weekly and Monthly project progress.
- Constantly interact with discipline leads; engineering, construction, procurement in the elaboration of the Project activities & control of their schedule
- Review scope change request for the impact on schedule and critical path of the project
- Maintain record of all changes in scope, activity logic or duration
- Control and monitor project total expenditure including verifying and checking of invoices and claims from suppliers, vendors and subcontractors to ensure that all project expenditures are captured and properly recorded.
- Provide planning and cost controlling support for all projects which includes variation reporting, monitoring of milestone progress to the preparation of customer billing processes
- Prepare monthly vessel movement report for the monitoring of the vessel activities on a daily basis and register all downtime, consumptions and vessel related issues relating to the project promptly to the project manager and management.
- Coordinate and work with the project management team to resolve project issues to ensure the delivery/completion of the project work.
- Attend project meetings and discussions with the PMT and external clients
- Perform project costing related reporting to the team and management on a monthly basis to ensure that expenditures are kept within the project budget.
- Provide cost control and planning advice to the internal PMT team as and when required.
Experience Hours (Planning & Scheduling):
1700
Experience Hours (Cost Management):
1200
Experience Hours (Forensic Analysis):
650
Links:
[1] http://www.planningplanet.com/category/skills-expertise/100-project-planning-cost-control-performance-monitoring-project-control-0
[2] http://www.planningplanet.com/category/training/100-project-planning-cost-control-budgeting-performance-monitoring-project-control
[3] http://www.planningplanet.com/category/project/fabrication-and-installation-offshore-platforms
[4] http://www.planningplanet.com/category/project/jackets-deck-section-and-topsides-subsea-structures
[5] http://www.planningplanet.com/category/industry/oil-gas-power
[6] http://www.planningplanet.com/category/project/procurement
[7] http://www.planningplanet.com/taxonomy/term/12883
[8] http://www.planningplanet.com/category/project/spm-buoys-and-manifolds-submarine-pipeline-and-platform-risers-pipeline-shore-cross
[9] http://www.planningplanet.com/category/project/templates-plem
[10] http://www.planningplanet.com/category/company/west-african-ventures-wav-limited
[11] http://www.planningplanet.com/category/project/%E2%80%A2-engineering
[12] http://www.planningplanet.com/category/region/africa-af/nigeria-afng