I have started with P6 few months ago.
My issue is:
Tracking progress on status tab: task Fixed Duration and Units, % complete type Physical. I chek the started, then Remaining days and % Physical based on actual and remaining days. If the task is delayed all resources updated however the actuals only updated accordingly the original duration. Why? How can I fix this?
Please help me.
My email: cfps5001@gmail.com [1]
Regards,
Carlos