Hi Guys,
Does anyone here has an insight on how P6 calculate total duration? the issue is, the original duration total or Baseline Duration is has higher number of days (although it is already a fixed date) than my actual duration when we have recorded delays; i.e. Sum of Activity 1 to 10 has 180 days baseline duration for 6 months while the actual duration only reflects 165 days while we are on our 8th month, (we are already delayed for 2 months) weird... is there i need to do and is the a walk-around on the matter to correct the problem? Thank you for the immediate response. Btw we are using only one calendar...
Cheers!
Ruel