I have a resource loaded project, and I would like to examine this project's resource allocation in P6 EPPM 18.8 Team Usage. But every time I select the Team Usage tab I get the below message:
Information: One or more projects are not published. Publish project to view data.
In addition to this message I find I cannot view any resource allocation data in this schedule, so soimething is wrong. The project I want to inspect is already published, so I'm not sure why I keep getting this message.
Any thoughts on what could be going wrong?