Dear all,I took on an EPC programme as a client-planner with three different contractors on it. At the end of the month, these three contractors submit their programmes separately, and I analysed and produced various reports for Senior Management curves, EVM etc The company have now asked me to develop an integrated masterworks programme not more than 300 – 500 activities and to show the critical path. The only overlap and dependencies in these EPC programmes when they are combined is when they get to commissioning stage. To add each of the programmes from the contractors contains more than 5000 activities I’ll like to be guided please on how I can go about this possibly using activity codes. Any help is most appreciated. Thank you