I have used P3, P5, and P6 for many years, but this latest version of Primavera P6 needs URGENT REVISING!
It is really troublesome, and I will AVOID IT as much as I can from now on!
1) Even though the Start Date considers constraints entered after the project has begun, the Finish Date value is NOT considering! Furthermore, the Finish Date considers the original Start date (without constraint) plus lag (if any), and can be entered DIRECTLY. In this case it will function more or less like a "Finish Milestone" - without being displayed as such!!
2) The Finish Date of Finish Milestones with many FF relationships is NOT selecting the latest one, but instead, it seems to use the "Finished" value in its Status.
Any help here?
Luiz Cruz