Hi everybody,
I got involved in delay analysis on motorway project, the Contract is under FIDIC Harmonised (MDB). We as Contractor received the contractual drawings on time, but from our side the submission was delayed 2 months beyond planned date in the Baseline programme.
My question is could the lack of right of way cause delay on the preparation and submission of road working drawings?
And what is the crusial information should have to prepare working drawings?
Any help appreciated..