Hi there!
I wanted to ask you planners out there, how to make an EOT claim in primavera? I have collected all the information about events and everything. I wanted to know how to present that in the program? I mean suppose an event that is delaying the project takes place on 20th July, which update to use? One after the event to show the impact or before it to forecast the impact? Also, what baseline to use? The approved baseline or we need to convert the prog into its baseline. Latter will show the exact delay, former may create issues for activities that are in progress.
Thanks