Hi,
I have an activity 4hrs in duration that needs to be completed within one working period (08hrs - 17hrs). Currently I have it on a calendar with non-working time (17hrs - 08hrs). If the activity starts too late (say at 15hrs on day one) it is split over the non-working period and completed in the second day at 10hrs. How do I stop the activity starting on the first day and moving it so that it starts and finishes (08hrs to 12hrs) on the second day.
Thanks in advance for your help