Hi
I'm quite new to planning / P6
And have a resource assignments question
I am trying to export the
1. Budgetted Units
2. Actual Units
3. Remaining Units
I go into the Resources Assisgnemrnt Tab and select one of the above and copy the information into excel
However. The units don't add up correctly? I.e
The Actual Units + Remaining Units do not add up to the Budgetted Units figure?
Any ideas?
Regards
Philip