Hello,
I need to compare Baseline Duration %Complete versus Actual Duration % Complete. I know that I can see this with "Schedule % Complete" column at activity level, not WBS Level. Schedule % Complete uses EV data for WBS. But what I need is to compare duration COmplete at WBS level. In order to do it, I created a dummy "duration" resource for each activity. Each activity's original duration is equal to its resources. I use this data when I export it to excel, not in primavera. Is there a way that I can creaye uSer defined column or etc. to calculate Baseline Planned Duration COmplete at WBS level?
Thank you.
Gulsah Erinc