WORK & Project HISTORY: 1996to Date (by Sector)
| |||
2012: Consultant / Provide Spreadsheet Solutions to DRIVER TRETT - To enable extraction of information from circa 100 individual spreadsheets in a simplified and understandable manner in order to compile associated claim | |||
| 2011: Consultant / Provide Spreadsheet Solutions to ENTERPRISE UTILITIES - To extract, handle, calculate and summarise data from and return findings to approx 93 individual spreadsheets associated with an EPC contract & further maintenance valued in the region of £80m+ | ||
| |||
| 2010: Provision of Tender Programmes for framework projects including Southend-on-Sea (£2.5m) continuing on to live progress reporting etc; Victoria Gateway & Deeping Closure; Progress Road; Cuckoo Corner: Carillion | ||
| 2009: Delay Analysis & prep of Advisory / Independent Review Documents for the client: Snowhill Railway Station Secondary Entrance, Birmingham: NR v Ed Nuttall Ltd | ||
| 2007: Network Rail Ltd (Employer): Assist in the preparation of contract documents ICE 7th for the Airdrie to Bathgate rail scheme of value £300 million (Scott Rail Glasgow) | ||
| 2005: P3/Excel Programme Analyst: Littlehampton ~ Amec / Systech | ||
| 2001-2002: Management/Claims presentation ~ CTRL Stratford (Vent Shafts valued at £25m) 4D modelling against programme to show different types, options & methods of design/construction (Conventional v Slipform) | ||
| 2001: Delay/Claims Analyst: Channel Tunnel Rail Links (CTRL) under NEC3~ Kvaerner (Ashford, Kent) | ||
| 1996-1999: Assist in Delay/Claims Analyst & Sub-Contract Accounts: Stratford Stn Redevelopment - JLEP ~ Kvaerner | ||
| 1998: Tender: D&B BoQ submission for Copenhagen Mini-metro ~ E Nuttall | ||
| 1998: Rail Maintenance: Assist in the assembling contractual terms etc for a Partnership proposals offered between Contractor & Client | ||
| |||
| 2009: Prepare Delay Analysis & Claims Document: Slough High Street Pedestrianisation: Enterprise v Slough Borough Council together with London Road, Improvement Scheme, Headington, Oxford: Enterprise v Oxfordshire County Council | ||
| 2009: Delay Analysis & prep of Claim Documents in connection with the Guildhall, London: Bovis Lend Lease | ||
| 2008: RNCMNR (Ministry of Transport Romania): Assist and support Expert in FIDIC Dispute Adjudication Board (DAB) for €13 million prolongation claim at Proodeftiki. | ||
| 2008: RNCMNR (Ministry of Transport Romania): Assist and support Expert Witness in FIDIC Dispute Adjudication Board (DAB) for €5 million claim on road rehabilitation scheme at Pantechniki, Romania. | ||
| 2007: RNCMNR (Ministry of Transport Romania): Assist and support Expert Witness in FIDIC Dispute Adjudication Board (DAB) for €18 million extension of time (EoT) claim with costs on road rehabilitation scheme knows as 4R13 | ||
| 2007: Colas (Contractor): Assist in the preparation and submission of a claim for €23 million of prolongation costs for road rehabilitation in Romania (FIDIC Conditions of Contract). | ||
| 2006-2008: RNCMNR (Ministry of Transport Romania): Assist and support Expert Witness in Delay Analysis to calculate interim extension of time and prolongation claim of €23 million for 150km of motorway construction (FIDIC Conditions of Contract) | ||
| 2006-2008: Romanian National Company of Motorways and National Roads (RNCMNR) (Ministry of Transport Romania): Assist and support Expert Witness in Delay Analysis to calculate interim extension of time and prolongation claim of €30 million for 23km of motorway construction (FIDIC Conditions of Contract) | ||
| 2001: Assist in the Tender of: A422 Hennef Way Dualling ~ Norwest Holst | ||
| 1992-1993: Deputy Resident Engineer on Sleaford By-Pass – New Construction including various junctions, bridges & culverts | ||
| 1991-1992: Resident Engineer on John Adams Way, Boston – Road Improvement Scheme incl associated traffic management | ||
| |||
| 1996: Delay/Claims Analyst: Assist in the preparation of a claim on works being carried out at RAF Lakenheath; | ||
| |||
| 2010: Claims / Delay Analyst / Forensic Planner: B&H Water Treatment Works 4D Brighton | ||
| |||
| 2010: Tender programme(s) & schedule of rates for various (9 in total) electrical maintenance & upgrade schemes: Utilities ~ Enterprise Utilities | ||
| 2010: Tender programme(s) & schedule of rates (& associated spreadsheet solutions) for various (11 in total) substation improvement schemes through the UK: Utilities Enterprise Utilities (Total Value £8.5m) | ||
| |||
| 1994-1995: Project Manager ~ Grantham Rail Bridge Refurbishment for Local Government Contractor | ||
| |||
2000: Marketing & Tender of works for Specialist Tunnelling Contractor. | |||
| |||
| 2006: Delay/Claims Analyst: St Alban’s Housing Refurbishment ~ **** | ||
| 2005-2007: MJ Gleeson v GE Frankona (Client): Assist in the assessment and response to a £2 million claim for damages associated with remedial works caused by dry rot during the conversion to and refurbishment of flats. | ||
| 2004-2005: Delay/Claims Analyst + Accounts: for extension of time claim associated with building services work at the new Wembley National Stadium, London, UK. | ||
| 2004: Delay/Claims Analyst: £15m Claim ~ Yarm Road & Cleveland Bridge -v- Hewden Tower Cranes Limited ~ Hewden Cranes Limited | ||
| 2002-2004: Delay/Claims Analyst for claims for extension of time and loss and expense incurred in the construction of Triton Square & Atlantic House, Holborn, London, UK ~ Skanska | ||
| 2002: Project Management on the Swiss Re Development (New London HQ – The Gerkin) ~ Skanska | ||
| 2001-2002: Delay/Claims Analyst: Harrods Crown Court Redevelopment ~ Kvaerner | ||
| 2001: Claims including Multimedia Presentations: ‘The Gate’ (Grade I Listed Bldg) ~ Skanska | ||
| |||
| 2005: QS / Commercial Support: Nottingham Beeston College ~ Jarvis Construction / Systech | ||
| |||
| 2005-2007Assist in the preparation and submission of a £20 million claim for delay and disruption to the regular progress of the works at Coventry Hospital: Skanska Coventry Joint Venture (Contractor) | ||
| 2003: Delay/Claims Analyst & S/C Accounts Analysis: Long Grove Hospital ~ NBA International Ltd / Bluestone | ||
| 2003: Assisting with Tender rates and schedules & phasing of works etc: Barts & London Hospital ~ Skanska | ||
| |||
| 2004: Delay/Claims Analyst: Wetherby New Build ~ Holroyd Construction | ||
| 2004: Delay/Claims Analyst: Wakefield Building Refurbishment ~ Holroyd Construction | ||
| 2004: Delay/Claims Analyst: Fulham Island Building Reconstruction and Refurbishment ~ Arbitration CZWG | ||
| |||
| 2017-2018 Veolia STI BU – Project in Finland (KPP / NJ) Claim schedule for EOT | ||
| 2017: Korea (KNPC) Claim narrative & schedule for EOT through Delay & Disruption; | ||
| 2016-2018: Jazan IGCC (EP): Biological, Oily Water & Metal Removal Treatment Packages, Saudi Arabia (Value: $60m) – including Claim for EOT & associated costs | ||
| 2016: Saudi Arabia (BP Kazzan) for Middle East BU – Claim for EOT & Associated costs resulting from delay & disruption | ||
| 2014-2016: SHELL Carmon Creek Project - New Oil Production Facility, Peace River, Alberta, Canada (Value: $435m) – Lead planner between 4 different BU’s around the world | ||
| 2015-2016: ECOPetrol, Columbia: Djeno Feed Study & Karbala Refinery (Value: $70m) | ||
| 2015: Planner: Tender & live schedule / reporting for the BP West Nile Delta Project (E) - Onshore Facility (Value: $4m)… early termination. | ||
| 2014-2015: Planner: Tender & live schedule / reporting for Tatweer I & III (WWTP TB 2, 3, 4, 1, 5 & 6) (EPC) – Bahrain (incl Claim(s) for EoT) (Value: $55m) | ||
| 2014-2015: Planner: Tender & live schedule / reporting for Tatweer New Tank Battery (NTB) (EPC) – Bahrain (Value: $15m) | ||
| 2014: Planner: Tender for Iraq West Qurna I (Tender) | ||
| 2014: Planner: Tender for SONARA Camaroon (draft for negotiations) | ||
| 2013: Planner: Tender for Qatar Petroleum (draft for negotiations) | ||
| 2011-2013: Planner: Tender & live planning / reporting for RMP2 Petron Daelim WWTP – Philippines (Value: $25m) | ||
| 2008: Romanian Ministry of Finance (Employer): Assist Expert advisor in a FIDIC DAB for €13 million prolongation claim on Timisoara Waste Water Treatment Plant. | ||
| 2006-2007: Veolia Environmental (Contractor): Assist in the preparation and submission of €30 million claim of Compensation Events that have caused delay and disruption to the construction of a water treatment works in Secunda, South Africa. (NEC Option B) | ||
| 2006: Delay/Claims Analyst: Isle of Grain ~ Skanska | ||
| 2011-2017: Numerous Oil & Gas (Water Tech) Tenders on behalf of Veolia, Paris | ||
| |||
| 2004: Tender/Programmer: £30m Nuclear Low Level Waste Prog. ~ Skanska Cementation. | ||
| |||
| 2008: Metinvest – Ukraine (Employer): Programme/Contracts Manager preparing P6 programme in association with NEC3 contract documents for procurement and management of contractors for the construction / extension of 3 iron and steel factories valued at €13 billion. | ||
| 2008: VAI – Defurco Contract: Delay Programme Presentation detailing Effected Works within Possession / Close Down Period of Steel Works | ||
| 2000-2003: Delay/Claims Analyst: CST – Hot Strip Mill, Brazil ~ VAI (UK) ltd valued at £280m |