Hi,
I have created a programme and created baseline(1) then shown impact of delays by rescheduling and created a further baseline (2)
I have then added further delays and rescheduled again to give the ovoerall delay.
I can find the overall delay by comparing live data to baseline (1) and displaying finish variance column howeverr I am looking to split the repsonibility of the delays.
Is there a way you can show the finish variance between baseline (1) and (2) in one column and the overall finish variance in another.
So far I have managed to create finish variance columns for the second delay by comapring finish to baseline (2) and overall delay by comparing finish with baseline (1) but as the first dealy is comparing two baselines rather than live data I cant think iof how to do this.
I have thought about creating formula based on overall and second delay but not sure how to do this .
Any advice?