In my current project that got handed over to me, I have 2 calendars. 95% of those are on Calendar 1 and 5% Calendar 2.
About 20% of activities have incorrect start and finish times (not starting at 8a or finishing at 5p) (although the dates are most possibly accurate)
Is there a quick way to fix this?
TIA