March, 2016 Lead Planner
Leading a team of 4 planners and responsible for planning, estimating and reporting progress in live projects as well a the creation of tender schedules for future wind farms.
- Nordsee One Offshore Wind Farm - Installation, burial and termination of 59x 33kV MVAC submarine composite cables.
- Veja Mate Offshore Wind Farm - Installation, burial and termination of 73x 33kV MVAC submarine composite cables.
- Beatrice Offshore Wind Farm - Installation, burial and termination of 91x 33kV MVAC submarine composite cables.
- Nordsee One HVAC export cable - Installation, burial and termination of 2x 155kV HVAC submarine composite cables.
Experience Hours (Planning & Scheduling):
2700
Experience Hours (Cost Management):
300