Hi,
There are few points which need your help as I am new to P6. Previously used asta powerproject.
a) I made few changes in my schedule but dont want to save these changes. How can I do that in P6?
Previously I used asta which had option save or not saved but in P6 there is no such option to close the project without saving the changes. P6 auto save the changes which is not required.
please suggest.
b)How to move the whole project to a new start date? any tip.
c)How can I hide any single row in P6?
d) How can I do baseline off in my project?
f) How can I do progress off in my whole project?
These all options are easily available in asta powerproject but in p6 facing problem to find the solution of these issues.
Please help
cheers
Andy