Hi,
While updating the schedule, I did some modifications in the activity relationships. In order to incorporate the same relationship changes in the Baseline Schedue (to do some analysis), I tried the Update Baseline option. I succeeded in getting the modified relationships of updated schedule to the baseline schedule. The issue is that the existing relationships of the baseline activities still remains there, and duplication of links happened.
Is there any option to replace the baseline existing activity relationships with the updated schedule relationship, while doing the exercise "Update Baseline"
Best Regards
Kannan