I am trying to allocate the use of 800 ton of 6N material to several tasks to allow me to assess the total daily demand.
Consumable resources cannot be levelled is there a way around this by perhaps using permanent resources?
I am struggling to ensure that the allocation is correct ie. 800t per day on each task to which the resource is assigned.
Any help will be much appreciated!