HI,
I have activities with resources, each Labour resource has its own Price/Unit, Max Units /Time is 100%, I have set Duration Type to Fixed Unit per Time because if I have to change the duration of the Activity I want to change as well the budgeted units.
I would like to automatically link the Budgted cost with budgeted Units as I have the cost per Unit and the Number of Budgeted Unit.
Ex: Duration is 10 days -> Working hours per day is 10 so I enter 100 Budgeted Unit
If I change duration for 12 days, my budgeted units become 120 which is fine, but my budgeted cost is not changing accordingly.
Is there a specific setting to change? I tried a Global Change but for Budgeted Cost it is not proposed
Thank you for your advices
Eric