Hi all
I am seeing more and more people wanting a line of balance set up as a spreadsheet, with each plot (housing project) down the left side and each activity along the top with the duration of each task identified, and then in each meeting cell a date of when the activity is to start.
If the activity starts on time it goes green and if it starts late it goes red.
Is there anyway of running a report from Asta to avoid having to manually transfer the info to excel?
Thanks in advance