HI,
I made a recovery programme, developed from the latest update of the approved baseline programme. Budget is loaded in the programme. In the activity spreadsheet of the recovery schedule, the budget seems to be distributed not as per the dates. Many activites have budget distribution even after the completion date.
In the activity spread sheet, I used the Budgeted Total Cost to see the budget distribution.
Is there any reason for it?
Thanks and Regards
Kannan