Hello everyone,
I am trying to update my actual blockwork quantites in p6. My activity type is physical % complete. I have physical % complete values. I manually enter all these values to units %complete in the activity details resource field. I want to have actual quantity that is equal to multiplication of budgeted units and units % complete. For some activities, it works. However, some activities do not give correct results.
Is there any suggestion?