START Date:
November, 2007
END Date:
November, 2009 Assist in decommissioning management system and database project tender activities, commissioning, implementation. INPP project management system developing. Details and achievements:
- Developed Integrated decommissioning Program which includes: new facilities constructions projects (EPC projects), dismantling activities and Milestones (technical design, procurement and implementation), Post-operation activities, Radioactive Waste treatment activities, Spent Fuel disposal activities.
- Elaborated and adjusted Work and Cost breakdown structure (WBS, CBS).
- Elaborated and adjusted Basic principles of feedback procedures, progress estimation indicators (Project progress measurement and KPI guideline).
- Elaborated and adjusted classification system for range of business categories developing and adjustment: resource, objects structures and other. This classification is used for annual financial requests developing and for any analytical purpose.
- Developed Cost calculation guideline. Practical labour unit’s allocation and cost calculation through all activities of Decommissioning Program.
- Developed Specifications and accepted additional software allowing actual data transferring to Primavera 6.1: actual cost from INPP accounting system (AXAPTA), actual labour units from master TIMESHIFT system.
Experience Hours (Planning & Scheduling):
500
Experience Hours (Cost Management):
500