So i have opened my schedule today in p6 and relised someone else has copy parts of my project into their's as they needed the same type of activities in there schedule.
However when they have copied and pasted the WBS it they seem to have had the Only between copied activiies un checked (in the copy activity options) and thus i now have hundreds of inter project links as it is maintaining those links from my schedule.
How can i quickly removed these as there are hundreds