Hi MSapiens/Planners,
I'm working on an MS Project file for quite sometime. It has got a baseline that was made long ago. Now, i want to see the critical path in that baseline. Can someone suggest me on sorting this out, using either custom filters or custom fields or any other possible means.
Thanks in advance.
Regards,
Siddharth