February, 2014 - Development of Design and Construction Programme for Phase 2 of the TRSP Depot project
- Experience of and utilization of Network Rail Grip 3,4 and 5-8 Methodology
- Attending wash up and work readiness meetingS
- Producing Hr by Hr possession programmes comprising of Civils/building, OLE and P-Way works
Experience Hours (Planning & Scheduling):