What is the correct method for linking a delay activity to the baseline programme?
Two colleagues have provided the following differing information.
1. The delay activity is linked to the predecessing / successing activity of the original planned activity.
2. The delay activity is linked to the same planned activity in the baseline programme.
Some clarity would be much appreciated.
Jonthan