in P6 R8.3.6, I want to move various labour resources on various activities to other existing activities. Some of the resources have been wrongly allocated, others need to move to a different time period.
I want to move the resources with the associated Resource Assignment UDF's.
Is there a way that I can drop and drag the resource and assigned codes from one activity to another in Resource Assignment Tab (similar to task drop and drag in Activities table)?
Or can I do it some other way - drop and drag/ copy & paste?
Plan B is to reassign using excel export/import (create and delete) - or is this the only way to do it without SQL access?