Hello,
Has somebody noticed that Microsoft dramatically changed the way resource leveling is computed since MS Project 2013?
Figure 1 shows a project sample leveled in MS Project 2010: task 8 has moved after task 5 as Resource 1 was overloaded
Figure 2 shows the same project leveled in MS Project 2013: task 5 is moved after task 8
Both projects have been leveled with all the leveling options de-activated; resources 1 and 1 have a 100% max. capacity in the resource sheet.
What could be the reason of that change?
Thank you for your help
Alexandre