START Date:
July, 2014 Assigned to the Eskom Power Utility Outage Control Centre and responsible for assuring the Business that planned outages will be will be effectively executed by site outage teams by:
- Defining Scope - Commencing at T-24 months, drive challenge and ensure scope freeze deadlines are met.
- Developing Timelines - Drive the production of realistic timelines for the execution of outages
- Proving Execution Readiness - Conducting Outage Readiness Reviews
- Managing the application and use of Time-Risk - Facilitate Recovery Planning when necessary on outages
- Continious Improvement - Carry out and report on Outage Post Mprtems and Lessons-Learnt
- Transfering Skills - Facilitate Planner mentorship through chairmanship of the Eskom Outage Planners Forum
Experience Hours (Planning & Scheduling):
5250