please note that i have for example project w/2 WBS:
- WBS #1 weight = 75% of the ABC Project
Included 2 activities
act #A weight = 60% of WBS #1
act #B weight = 40% of WBS #1
- WBS #2 weight = 25% of the project
Included 2 activities
act #C weight = 35% of WBS #2
act #D weight = 65% of WBS #2
I need this data appears as follows in the schedule as activities weights not activities steps weights:
Activity ID Activity Name | Weight | |
ABC Project | 100% | |
WBS #1 | 75% | |
10 Act #A | 60% | |
20 Act #B | 40% | |
WBS #2 | 25% | |
30 Act#C |
35% | |
40 Act#D | 65% |
regarding that i will use the above in updating progress.
please clarify in clear steps and snapshots if available.