I just created a cost loaded schedule and everything look fine. The problem is that everytime and re-run the schedule the budgeted cost changes on me and it driving me crazy. This only happen on a particular resource. P6 always always add or subtract some decimal points to whatever I input. For example, $350,000 would change to $349,999.78. What is going on?