I have always used 8hrs/day calendar but I just got a project that requires a 24/7 calendar. The way 24hrs/day calendar works in P6 really throws me offguard.
In 8hrs/day calendar, work starts at 8am and ends at 5pm on the same day. The successor activty starts at 8am the next day. I was hoping the same situation would apply to 24hrs/day calendar. In 24hrs/day calendar, work start 12am day1 and ends 12am day2. The successor activity starts 12am day2 and ends 12am day3.
I really want work to start and finish on the same day instead of shifting to the next day. Does anyone have a solution to this or any suggestion?