Hi,
Currently we track revenue [what we can claim from the client] by assigning a value loaded Non-Labour Resource to each activity, this is fine for measuring individual values per activity, but for overheads [Security/Welfare etc..] we assign them to a WBS Summary bar.
Now my question is, if we had a project that lasted 10 days, and the Value is £10 per day, today is day 5 and I have updated the schedule and we have claimed £50 but now we have a delay and the project is going to take another 7 days [so an extension of 2 days].
When I now update the project the Actual Cost [what we should & have claimed] will now drop and the remaining cost will rise, but obviously we have already claimed 50% so how do I get primavera to stand its ground on the actuals?
Thanks
Harry