I have a schedule in which I am using 2 different calendars. One for Design activity which is 6DX8hrs working and the other is construction whihc is 7X22hrs working. Since, construction activities domiated design, I have considered default working hrs as 22hrs & 7 days in a week as working. I have assigned the task calendar according to the nature of activity viz-a-viz design or construction.
Now, the issue I am facing is if I make the duration of design (with 6DX8hrs design calndar assigned to it) activity say for example as 1 day, MSP considers as 3 days i.e., equivalent of 22 hrs per day by default. If my start date is 01st October, my finish date should be 01st October as duration is 1 day, but I am getting the finish date as 3rd October.
Kindly anybody explain how to resolve this.