Dear All,
To summarise in short, the project I'm working has elapsed 10months and further 6months to complete. But due to several delay reasons an EOT was awarded for 3more months and requires change of logics for many activities.
Now, the Engineer had asked for a "Revised Baseline Programme". Kindly advise which out of the following is the best practise :
1) Revise the last update and submit the programme with Actuals and Data Date being latest update date....or
2) Have to destatus the Revised lastest update, removing actuals and the Data Date being Start of Contract date......