After some searching I have not been able to locate a solution yet. Hopefully someone can point me in the right direction.
In my schedule I have 4 milestones:
Section 1, Section 2, Section 3 and Section 4.
Each section consists of different buildings. I would to create a filter that shows the activities driving each milestone.
I can easily create a critical path and longest path filter to see the overall project. But I really need to see what activities are driving each section.
Thanks for your help!
Robby