Hi all,
I started this thread to discuss a avery strange case of total float i encountered..
I had prepared a microprogram for a small section of work which I had checked all links,dates and had the correct finish date as planned with a total float of 0.
Some activities were in progrss and had actuals.I exported this project and send it to the client as well.
I assigned it a baseline and started updating weekly.
Two weeks later,I had to add an activity to the baseline microprogram.I imported it back and when I scheduled it,it shows a negative total float of -6!!
The data date is same as before and I checked the calendar as well.
Im facing this issue for the first and can't seem to find a proper solution;any advice will be helpful
Thanks in advance