Hi to all! I am a bit confused regarding default units/time for any resource matreial specially concrete.Somebody informed me that put ZERO in default units/time in any material resource and after doing this the budgeted units also become zero.Please suggest or guide me what is the correct thing in any Material resource case in P6.