Hopefully someone can help
I have exported from the resource and resource assignments from p6 into excel
and i have changed a number of the quanitites (ensuring the numbers remain as labels)
however, when i import the excel file back in,it only seems to populate 1 resource against each activity, ignoring the others
can anyone advise
thanks
Simon Hegarty