Dear all,
Please help me out in couple of queries
1) I have budgeted labour, budgeted non labour (equipment hrs) units for each activity in project. when i calculate progress based on budgeted units alone do i have to consider only labour units as this is direct or consider both and total them and then compare progress.(duration type is fixed units since it is units driven)
2) my activity duration is say 10 days original, budgeted units say 1000 man hrs, the activity is already started and it is 60 percent complete, ie remaining units would be 400 units, and remaining duration 4 days. but the activity still requires another 5 more days making it duration at complete as 15. ie remaining duration is now 9 days(4d+5d). will that change my units at complete from 1000 to 1500? In case it changes to 1500 wat does it actually imply. is it a profit or loss for that activity.
3) when initially considering the budgeted units, if an activity has 1000 man hrs. wat if in an activity the manpower has more OT and in other words it would go beyond 1000 man hrs right practically. is it the right way.