Hi,
I have a list of resources and their budgeted hours on a monthly basis in excel and would like to import this list into P6.
In P6 i have the list of resources which already have actual hours accrued as well as remaining hours.
The requirements are as follows:
1. To ensure that the resource usage spread on a month by month basis from P6 tallies with that in Excel.
2. Minimal effort to ensure the two reports tally.
I was wondering if anyone here has faced similar requirements, and how you have gone about resolving this.