Good day !
This is my first post in this forum. Glad if someone who reading this willing to help.
My senior planner recently has sent me a Baseline programme in XER file, I try to open the file, but the Baseline start and finish date is different from his computer. I have double check the file to find out that we use the same XER file. My computer showing -2 days different from the actual finish date. I have deleted the project and import it back, yet still having the same problem.
We have use the same calendar with him. In addition, we are using the same P6 8.2 version.
I would apreciate if you can help me about this problem.
Cheers
Wan