Dear Ladies and Gentlemen,
Kindly advice me with the correct assesment on Contractor's Claim. I have a discussion with the PMC since he is applying his method for giving entitlement on Contractors Claim. PMC requested 2 seperate programs since there are two events. Second, he use baseline program and run apply actuals. He said that this method is used widely for assesing the claim. The 2 Impacted programs also he asked from the COntractor is baseline with a zero progress for both. I felt that what he is doing is wrong. In my understanding, you have to use the Latest Progress Update which is exerpt from the approved baseline program.
Regards,