Dear All ,
While loading a cost for my project , i tried to assign the resources for general activities ( e.g. Indirect manpower cost or laydown cost ) to a " Level of effort activity " .
But while updating those LOE activities, i observed that there are no Earned value calculations for those activities .
Is there any way to fix this problem or this is an attribute to LOE activity?