Hi all,
New to the forum, signed up specifically to ask this question.
I'm trying to add actuals to a plan of mine and I'm zoomed in so I can see the days within the week. When I assign, say, 40 units over 5 days, it will split it:
Mon: 8 Tue: 8 Wed: 8 Thu: 8 Fri 8
I receive timesheets where the units are irregular and are not linearly spread, for example:
Mon 6: Tue: 10 Wed 7.5 : Thur: 8.25 Fri: 8.25
Is there any way, when in the resource assignments view, with the table displaying actual units, to have it display the actual units spent rather than it spreading it linearly?
Kind regards,
Lewis.